Track your team's average story-point delivery per sprint and use it to make reliable capacity commitments.

Screenshot: Velocity chart — rolling 8-sprint view

Reading the Velocity chart

  • Bars — story points completed per sprint (Done stories only — not In Progress at sprint close)
  • Rolling average line — the average of the last N sprints (configurable: 3, 5, or 8). Use this as your planning benchmark, not the most recent sprint
  • Commitment line — what was planned for each sprint. The gap between planned and completed is your sprint over/under-commitment

Using velocity for planning

The rolling average is the most reliable predictor of what the team can deliver next sprint. Add 15—20% buffer for unplanned work. Use this figure as the upper limit when planning.

💡 Velocity is only meaningful after 3+ sprints. Don't use a single sprint's result as a planning benchmark.

Velocity vs. capacity

Velocity (historical) and Capacity (forward-looking) are related but distinct:

  • Capacity = team members — sprint days — points per day = theoretical maximum
  • Velocity = actual story points completed per sprint = realistic throughput

Use velocity for sprint planning commitments. Use capacity to identify headroom and model the impact of team composition changes.